Synchronous Operation of Four Truck Cranes for the Installation of an Industrial Overhead Crane in Udine Province
Description of the task assigned to MIDLIFT
The project involved the installation of a 30-ton industrial overhead crane, preassembled on the ground, inside a production facility. Due to the large size of the structure and the limited height of the building, the traditional setup with two mobile cranes could not be adopted.
Solutions developed by MIDLIFT Technical Department
The initial plan envisaged placing a mobile crane outside the building and creating an opening in the roof to lower the hook inside for lifting. However, following the client’s request for a less invasive alternative, MIDLIFT designed and executed a synchronous lifting configuration using four specialized truck-mounted cranes arranged in pairs on both sides of the beam.
Preparatory operations for lifting
The client ensured the safety of electrical cabling, removed obstacles within the work area, and welded reference stops at the base of the beams to prevent chain slippage during lifting. Using two existing overhead cranes, the new one was moved into the optimal lifting position.
The intervention with the four MIDLIFT truck cranes
The four truck cranes were positioned according to the executive project to ensure safe working conditions and proper clearance from roof trusses. After connecting the chains to the hooks and extending the telescopic booms to the required length, the lifting operations began. The maneuver involved a transverse lift to overcome the runway beams and achieve the correct final positioning.
Eurogrù Amici 21.33 (nominal capacity: 130 tons)
Eurogrù Amici 150.35 (nominal capacity: 150 tons)
Idrogru KT 160.33 (nominal capacity: 160 tons)
Truck Crane MAN + Fassi F1650RAL.2.28 (nominal capacity: 24.5 tons)